Development of a new delay analysis method that considering schedule updates and resource over allocation

العناوين الأخرى

تطوير طريقة لتحليل التأخير تراعي تحديثات الجدول الزمني و التخصيص الزائد للمصادر.

مقدم أطروحة جامعية

Jendeya, Ihab R.

مشرف أطروحة جامعية

Rustum, Rifat N.

الجامعة

الجامعة الإسلامية

الكلية

كلية الهندسة

القسم الأكاديمي

قسم الهندسة المدنية

دولة الجامعة

فلسطين (قطاع غزة)

الدرجة العلمية

ماجستير

تاريخ الدرجة العلمية

2009

الملخص الإنجليزي

Due to the inherent risks and increasing complexity of modern construction projects, delays and cost overruns have become common facts in the industry.

Researchers and practitioners have used many techniques to assess project delays and apportion delay responsibility among the parties involved.

Windows delay analysis has been recognized as one of the most credible techniques for analyzing construction delays.

Despite its benefits, windows analysis can produce different results depending on the window size, it does not consider owner and contractor acceleration, it does not systematically consider the impact of several schedule updates made due to changes in the duration and logical relationships of the activities, and it does not consider the impact of the progress events on resource over-allocation and its consequent delays.

This study proposes a new schedule analysis model that considers multiple schedule updates and resource over-allocation.

The model uses a daily window size in order to consider all fluctuations in the critical path(s) and uses a legible representation of progress information to accurately apportion delays and accelerations among project parties.

A simple case study has been demonstrated on the proposed delay analysis model in order to validate its accuracy and usefulness.

To facilitate its use, the study has been introduced detailed procedures to make the control process on the scheduling and resource management through the project period is easy process.

التخصصات الرئيسية

الهندسة المدنية

الموضوعات

عدد الصفحات

123

قائمة المحتويات

Abstract.

Table of contents.

Chapter one : Introduction.

Chapter two : Literature review.

Chapter three : Modified daily windows analysis method considering schedule updates.

Chapter four : Modified daily windows analysis method considering resource allocation.

Chapter five : Conclusion & recommendation.

References.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

Jendeya, Ihab R.. (2009). Development of a new delay analysis method that considering schedule updates and resource over allocation. (Master's theses Theses and Dissertations Master). Islamic University, Palestine (Gaza Strip)
https://search.emarefa.net/detail/BIM-301721

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

Jendeya, Ihab R.. Development of a new delay analysis method that considering schedule updates and resource over allocation. (Master's theses Theses and Dissertations Master). Islamic University. (2009).
https://search.emarefa.net/detail/BIM-301721

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

Jendeya, Ihab R.. (2009). Development of a new delay analysis method that considering schedule updates and resource over allocation. (Master's theses Theses and Dissertations Master). Islamic University, Palestine (Gaza Strip)
https://search.emarefa.net/detail/BIM-301721

لغة النص

الإنجليزية

نوع البيانات

رسائل جامعية

رقم السجل

BIM-301721