Robust Proactive Project Scheduling Model for the Stochastic Discrete TimeCost Trade-Off Problem

المؤلفون المشاركون

Li, Hongbo
Xu, Zhe
Xiong, Li
Liu, Yinbin

المصدر

Discrete Dynamics in Nature and Society

العدد

المجلد 2015، العدد 2015 (31 ديسمبر/كانون الأول 2015)، ص ص. 1-10، 10ص.

الناشر

Hindawi Publishing Corporation

تاريخ النشر

2015-03-19

دولة النشر

مصر

عدد الصفحات

10

التخصصات الرئيسية

الرياضيات

الملخص EN

We study the project budget version of the stochastic discrete time/cost trade-off problem (SDTCTP-B) from the viewpoint of the robustness in the scheduling.

Given the project budget and a set of activity execution modes, each with uncertain activity time and cost, the objective of the SDTCTP-B is to minimize the expected project makespan by determining each activity’s mode and starting time.

By modeling the activity time and cost using interval numbers, we propose a proactive project scheduling model for the SDTCTP-B based on robust optimization theory.

Our model can generate robust baseline schedules that enable a freely adjustable level of robustness.

We convert our model into its robust counterpart using a form of the mixed-integer programming model.

Extensive experiments are performed on a large number of randomly generated networks to validate our model.

Moreover, simulation is used to investigate the trade-off between the advantages and the disadvantages of our robust proactive project scheduling model.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

Li, Hongbo& Xu, Zhe& Xiong, Li& Liu, Yinbin. 2015. Robust Proactive Project Scheduling Model for the Stochastic Discrete TimeCost Trade-Off Problem. Discrete Dynamics in Nature and Society،Vol. 2015, no. 2015, pp.1-10.
https://search.emarefa.net/detail/BIM-1060689

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

Li, Hongbo…[et al.]. Robust Proactive Project Scheduling Model for the Stochastic Discrete TimeCost Trade-Off Problem. Discrete Dynamics in Nature and Society No. 2015 (2015), pp.1-10.
https://search.emarefa.net/detail/BIM-1060689

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

Li, Hongbo& Xu, Zhe& Xiong, Li& Liu, Yinbin. Robust Proactive Project Scheduling Model for the Stochastic Discrete TimeCost Trade-Off Problem. Discrete Dynamics in Nature and Society. 2015. Vol. 2015, no. 2015, pp.1-10.
https://search.emarefa.net/detail/BIM-1060689

نوع البيانات

مقالات

لغة النص

الإنجليزية

الملاحظات

Includes bibliographical references

رقم السجل

BIM-1060689