Sequential Measurement and Analysis of Large Underground Retaining Structures by Diaphragm Wall Anchor for the Spring Area

المؤلفون المشاركون

Zhang, Dingwen
Shu, Jicheng
Sun, Jianping
Wei, Huanwei

المصدر

Advances in Civil Engineering

العدد

المجلد 2019، العدد 2019 (31 ديسمبر/كانون الأول 2019)، ص ص. 1-21، 21ص.

الناشر

Hindawi Publishing Corporation

تاريخ النشر

2019-11-11

دولة النشر

مصر

عدد الصفحات

21

التخصصات الرئيسية

هندسة مدنية

الملخص EN

The performance of a diaphragm wall-anchor structure in spring area in Jinan city, China, is studied.

Based on field measured data, lateral wall deflections, lateral soil movements, horizontal displacement of the capping beam, the maximum lateral wall deflection, ground surface settlement, lateral earth pressures on diaphragm wall, internal force of diaphragm wall, axial anchoring forces, settlements of adjacent building, and pore-water pressure are investigated.

The results indicate that the maximum deflections of the lateral wall are 0.07%∼0.18% of the excavation depth (He).

The ground surface settlement influence zone extends beyond 2.5He from the pit for this project.

The δv,max ranges from 0.67 δh,max to 1.0 δh,max.

The maximum lateral active earth pressures on diaphragm walls above the excavation bases range between 0.4He and 0.6He.

The axial anchoring forces of the top three layers of anchors change significantly during the excavation while the axial anchoring force of the fourth layer of anchor is constant.

The deformation of surrounding building has three stages, including a uniform subsidence stage, an accelerated subsidence stage, and a stable subsidence stage.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

Shu, Jicheng& Sun, Jianping& Zhang, Dingwen& Wei, Huanwei. 2019. Sequential Measurement and Analysis of Large Underground Retaining Structures by Diaphragm Wall Anchor for the Spring Area. Advances in Civil Engineering،Vol. 2019, no. 2019, pp.1-21.
https://search.emarefa.net/detail/BIM-1116480

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

Shu, Jicheng…[et al.]. Sequential Measurement and Analysis of Large Underground Retaining Structures by Diaphragm Wall Anchor for the Spring Area. Advances in Civil Engineering No. 2019 (2019), pp.1-21.
https://search.emarefa.net/detail/BIM-1116480

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

Shu, Jicheng& Sun, Jianping& Zhang, Dingwen& Wei, Huanwei. Sequential Measurement and Analysis of Large Underground Retaining Structures by Diaphragm Wall Anchor for the Spring Area. Advances in Civil Engineering. 2019. Vol. 2019, no. 2019, pp.1-21.
https://search.emarefa.net/detail/BIM-1116480

نوع البيانات

مقالات

لغة النص

الإنجليزية

الملاحظات

Includes bibliographical references

رقم السجل

BIM-1116480