Resource Unconstrained and Constrained Project Scheduling Problems and Practices in a Multiproject Environment
المؤلفون المشاركون
Kannimuthu, Marimuthu
Ekambaram, Palaneeswaran
Raphael, Benny
Kuppuswamy, Ananthanarayanan
المصدر
العدد
المجلد 2018، العدد 2018 (31 ديسمبر/كانون الأول 2018)، ص ص. 1-13، 13ص.
الناشر
Hindawi Publishing Corporation
تاريخ النشر
2018-07-15
دولة النشر
مصر
عدد الصفحات
13
التخصصات الرئيسية
الملخص EN
Construction companies execute many projects simultaneously.
In such situations, the performance of one project may influence the others positively or negatively.
Construction professionals face difficulties in managing multiple projects in limited resource situations.
The purpose of this study is to identify the problems in multiproject scheduling from the practitioner’s perspective and to discover current practices under resource unconstrained and constrained settings.
The specific objectives are (1) determining the most challenging issues being faced in handling multiproject environment, (2) enumerating the practices adopted in the industry, and finally (3) identifying the practitioners' perceptions on the multiproject scheduling aspects such as network modeling approaches; activity execution modes; concept of sharing, dedicating, and substituting resources; centralized and decentralized decision-making models; solution approaches; and tools and techniques.
An online questionnaire survey was conducted to address the objectives above.
The top challenging issues in managing multiproject environment are identified.
Factor analysis identified the factors by grouping the variables (a) decision-related, (b) project environment-related, (c) project management-related, and (d) organization-related factors.
Resource-unconstrained situation mainly faces the issue of underutilization and wastage of resources leading to lower profit realization.
The following findings were identified to overcome the unconstrained resource situation such as identifying the work front, adopting pull planning approach, creating a common resource pool, and allotting it on a rental basis.
On the contrary, resource-constrained situation faces the issues of prioritization of resources, coordination, communication, collaboration, quality issues, and rework.
The findings suggest the strategies such as top-up via subcontracting, proactive pull planning, introducing buffers, training the culture of the organization towards better communication, coordination, and collaboration, to improve the reliability of achieving baseline project performances.
Various multiproject aspects suggested for effective management.
The identified problems, practices, and various multiproject aspects are expected to contribute better management of multiproject resource unconstrained and constrained project scheduling.
نمط استشهاد جمعية علماء النفس الأمريكية (APA)
Kannimuthu, Marimuthu& Ekambaram, Palaneeswaran& Raphael, Benny& Kuppuswamy, Ananthanarayanan. 2018. Resource Unconstrained and Constrained Project Scheduling Problems and Practices in a Multiproject Environment. Advances in Civil Engineering،Vol. 2018, no. 2018, pp.1-13.
https://search.emarefa.net/detail/BIM-1116958
نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)
Kannimuthu, Marimuthu…[et al.]. Resource Unconstrained and Constrained Project Scheduling Problems and Practices in a Multiproject Environment. Advances in Civil Engineering No. 2018 (2018), pp.1-13.
https://search.emarefa.net/detail/BIM-1116958
نمط استشهاد الجمعية الطبية الأمريكية (AMA)
Kannimuthu, Marimuthu& Ekambaram, Palaneeswaran& Raphael, Benny& Kuppuswamy, Ananthanarayanan. Resource Unconstrained and Constrained Project Scheduling Problems and Practices in a Multiproject Environment. Advances in Civil Engineering. 2018. Vol. 2018, no. 2018, pp.1-13.
https://search.emarefa.net/detail/BIM-1116958
نوع البيانات
مقالات
لغة النص
الإنجليزية
الملاحظات
Includes bibliographical references
رقم السجل
BIM-1116958
قاعدة معامل التأثير والاستشهادات المرجعية العربي "ارسيف Arcif"
أضخم قاعدة بيانات عربية للاستشهادات المرجعية للمجلات العلمية المحكمة الصادرة في العالم العربي
![](/images/ebook-kashef.png)
تقوم هذه الخدمة بالتحقق من التشابه أو الانتحال في الأبحاث والمقالات العلمية والأطروحات الجامعية والكتب والأبحاث باللغة العربية، وتحديد درجة التشابه أو أصالة الأعمال البحثية وحماية ملكيتها الفكرية. تعرف اكثر
![](/images/kashef-image.png)