Robust Optimization for Integrated Construction Scheduling and Multiscale Resource Allocation

المؤلفون المشاركون

Li, Qian
Chong, Heap-Yih (John)
Tao, Sha
Dong, Zhijie Sasha

المصدر

Complexity

العدد

المجلد 2018، العدد 2018 (31 ديسمبر/كانون الأول 2018)، ص ص. 1-17، 17ص.

الناشر

Hindawi Publishing Corporation

تاريخ النشر

2018-07-24

دولة النشر

مصر

عدد الصفحات

17

التخصصات الرئيسية

الفلسفة

الملخص EN

This research investigates an integrated problem of construction scheduling and resource allocation.

Inspired by complex construction practices, multi-time scale resources are considered for different length of terms, such as permanent staff and temporary workers.

Differing from the common stochastic optimization problems, the resource price is supposed to be an uncertain parameter of which probability distribution is unknown, but observed data is given.

Hence, the problem here is called Data-Driven Construction Scheduling and Multiscale Resource Allocation Problem (DD-CS&MRAP).

Based on likelihood robust optimization, a multiobjective programming is developed where project completion time and expected resource cost are minimized simultaneously.

To solve the problem efficiently, a double-layer metaheuristic comprised of Multiple Objective Particle Swarm Optimization (MOPSO) and interior point method named MOPSO-interior point algorithm is designed.

The new solution presentation scheme and decoding process are developed.

Finally, a construction case is used to validate the proposed method.

The experimental results indicate that the MOPSO-interior point algorithm can reduce resource cost and improve the efficiency of resource utilization.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

Li, Qian& Tao, Sha& Chong, Heap-Yih (John)& Dong, Zhijie Sasha. 2018. Robust Optimization for Integrated Construction Scheduling and Multiscale Resource Allocation. Complexity،Vol. 2018, no. 2018, pp.1-17.
https://search.emarefa.net/detail/BIM-1133326

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

Li, Qian…[et al.]. Robust Optimization for Integrated Construction Scheduling and Multiscale Resource Allocation. Complexity No. 2018 (2018), pp.1-17.
https://search.emarefa.net/detail/BIM-1133326

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

Li, Qian& Tao, Sha& Chong, Heap-Yih (John)& Dong, Zhijie Sasha. Robust Optimization for Integrated Construction Scheduling and Multiscale Resource Allocation. Complexity. 2018. Vol. 2018, no. 2018, pp.1-17.
https://search.emarefa.net/detail/BIM-1133326

نوع البيانات

مقالات

لغة النص

الإنجليزية

الملاحظات

Includes bibliographical references

رقم السجل

BIM-1133326