Solution of uncertain resource allocation problem in activity networks for project management
مقدم أطروحة جامعية
مشرف أطروحة جامعية
أعضاء اللجنة
Tarawinah, Sultan A.
Abu Rumman, Ayman
الجامعة
جامعة الإسراء
الكلية
كلية الهندسة
دولة الجامعة
الأردن
الدرجة العلمية
ماجستير
تاريخ الدرجة العلمية
2014
الملخص الإنجليزي
In construction management, the objective is to define and develop a solution and a model for planning, scheduling, controlling and monitoring the activities of the project.
The time scheduling plays a very important role in success of the proper implementation of the various activities and general outcome of the project.
In practice, because of many reasons, most projects suffer from time delay in accomplishing the activities.
One important reason is the non-exacting knowledge about the time duration of activities.
This research deals with the problem of construction project scheduling with uncertain resource environments, which are defined by uncertain activity durations.
It considers the solution of the leveling and allocation problems for projects that have some uncertain activities. The resources are minimized and redistributed using resource leveling that is based on a proposed heuristic algorithm with limited duration time.
The algorithm performs the resource scheduling (leveling and allocation) for minimum moments.
The efficiency of the proposed algorithm is indicated by the resource improving coefficient and the rate of resource's utilization.
As a case-study, the electric works in a hospital rehabilitation project, in Iraq-Baghdad, is used to explore the application of the proposed algorithm.
التخصصات الرئيسية
العلوم الهندسية والتكنولوجية (متداخلة التخصصات)
الموضوعات
عدد الصفحات
89
قائمة المحتويات
Table of contents.
Abstract.
Chapter One : Introduction.
Chapter Two : literature review.
Chapter Three : Research methodology and mathematical model.
Chapter Four : Results and analysis.
Chapter Five : Conclusions and future works.
References.
نمط استشهاد جمعية علماء النفس الأمريكية (APA)
al-Duri, Rim Zakariyya. (2014). Solution of uncertain resource allocation problem in activity networks for project management. (Master's theses Theses and Dissertations Master). Isra University, Jordan
https://search.emarefa.net/detail/BIM-422454
نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)
al-Duri, Rim Zakariyya. Solution of uncertain resource allocation problem in activity networks for project management. (Master's theses Theses and Dissertations Master). Isra University. (2014).
https://search.emarefa.net/detail/BIM-422454
نمط استشهاد الجمعية الطبية الأمريكية (AMA)
al-Duri, Rim Zakariyya. (2014). Solution of uncertain resource allocation problem in activity networks for project management. (Master's theses Theses and Dissertations Master). Isra University, Jordan
https://search.emarefa.net/detail/BIM-422454
لغة النص
الإنجليزية
نوع البيانات
رسائل جامعية
رقم السجل
BIM-422454
قاعدة معامل التأثير والاستشهادات المرجعية العربي "ارسيف Arcif"
أضخم قاعدة بيانات عربية للاستشهادات المرجعية للمجلات العلمية المحكمة الصادرة في العالم العربي
تقوم هذه الخدمة بالتحقق من التشابه أو الانتحال في الأبحاث والمقالات العلمية والأطروحات الجامعية والكتب والأبحاث باللغة العربية، وتحديد درجة التشابه أو أصالة الأعمال البحثية وحماية ملكيتها الفكرية. تعرف اكثر