Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

المؤلفون المشاركون

Shields, David R.
Burns, Leslie A.
Shrestha, Pramen P.

المصدر

Journal of Construction Engineering

العدد

المجلد 2013، العدد 2013 (31 ديسمبر/كانون الأول 2013)، ص ص. 1-9، 9ص.

الناشر

Hindawi Publishing Corporation

تاريخ النشر

2013-12-18

دولة النشر

مصر

عدد الصفحات

9

التخصصات الرئيسية

هندسة مدنية

الملخص EN

This study analyzed 363 Clark County Department of Public Works (CCDPW) projects to determine construction cost and schedule overruns in various types and sizes of the projects.

The sample projects were constructed from 1991 to 2008, with a total construction cost of $1.85 billion, equivalent to 2012 cost.

A one-factor ANOVA test was conducted to determine whether construction cost and schedule overruns significantly varied based on types and sizes of the projects.

The study showed that large, long-duration projects had significantly higher cost and schedule overruns than smaller, short-duration projects.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

Shrestha, Pramen P.& Burns, Leslie A.& Shields, David R.. 2013. Magnitude of Construction Cost and Schedule Overruns in Public Work Projects. Journal of Construction Engineering،Vol. 2013, no. 2013, pp.1-9.
https://search.emarefa.net/detail/BIM-509532

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

Shrestha, Pramen P.…[et al.]. Magnitude of Construction Cost and Schedule Overruns in Public Work Projects. Journal of Construction Engineering No. 2013 (2013), pp.1-9.
https://search.emarefa.net/detail/BIM-509532

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

Shrestha, Pramen P.& Burns, Leslie A.& Shields, David R.. Magnitude of Construction Cost and Schedule Overruns in Public Work Projects. Journal of Construction Engineering. 2013. Vol. 2013, no. 2013, pp.1-9.
https://search.emarefa.net/detail/BIM-509532

نوع البيانات

مقالات

لغة النص

الإنجليزية

الملاحظات

Includes bibliographical references

رقم السجل

BIM-509532