An analysis of causes and factors affecting change orders occurrence in construction projects in Iraq
المؤلفون المشاركون
Wali, Khalil Ismail
Sabir, Nazik Imad
المصدر
ZANCO Journal of Pure and Applied Sciences
العدد
المجلد 31، العدد 6 (31 ديسمبر/كانون الأول 2019)، ص ص. 1-12، 12ص.
الناشر
جامعة صلاح الدين قسم النشر العلمي
تاريخ النشر
2019-12-31
دولة النشر
العراق
عدد الصفحات
12
التخصصات الرئيسية
الملخص EN
One of the most important problems facing the construction management process is the occurrence of change orders, which became inevitable in every construction project and the magnitude of these variations varies considerably from project to project.
Considerably causing different effects to the project like changes in cost, time, quality, and completion schedule.
The objective of this study is analyzing change orders causes related to owner, contractor, consultant and other causes and their effects on project cost for the Kirkuk governorate-Iraq selected as a case study for the purpose of this paper.
The Relative Importance Index (RII) methodology was used to analysis the collected data.
The case study analysis focused on the selection of 12 construction projects and a questionnaire administered to professionals in the construction industry in Iraq.
According to the questionnaire analysis of 40 questions and based on RII ranking was found that the top most ten significant causes of the change orders come to the poor project management in the first rank.
Whereas, change in the country’s economic conditions comes in the second rank, contractor’s lack of experience and mistakes during construction stage, poor cost estimation, quality assurance and control, poor performance of contract and subcontractor, the contractor’s financial difficulties, the lack of required skills, unrealistic project durations and design errors and omissions, and finally the collision between contract documents.
نمط استشهاد جمعية علماء النفس الأمريكية (APA)
Wali, Khalil Ismail& Sabir, Nazik Imad. 2019. An analysis of causes and factors affecting change orders occurrence in construction projects in Iraq. ZANCO Journal of Pure and Applied Sciences،Vol. 31, no. 6, pp.1-12.
https://search.emarefa.net/detail/BIM-949347
نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)
Wali, Khalil Ismail& Sabir, Nazik Imad. An analysis of causes and factors affecting change orders occurrence in construction projects in Iraq. ZANCO Journal of Pure and Applied Sciences Vol. 31, no. 6 (2019), pp.1-12.
https://search.emarefa.net/detail/BIM-949347
نمط استشهاد الجمعية الطبية الأمريكية (AMA)
Wali, Khalil Ismail& Sabir, Nazik Imad. An analysis of causes and factors affecting change orders occurrence in construction projects in Iraq. ZANCO Journal of Pure and Applied Sciences. 2019. Vol. 31, no. 6, pp.1-12.
https://search.emarefa.net/detail/BIM-949347
نوع البيانات
مقالات
لغة النص
الإنجليزية
الملاحظات
Includes bibliographical references : p. 11-12
رقم السجل
BIM-949347
قاعدة معامل التأثير والاستشهادات المرجعية العربي "ارسيف Arcif"
أضخم قاعدة بيانات عربية للاستشهادات المرجعية للمجلات العلمية المحكمة الصادرة في العالم العربي
تقوم هذه الخدمة بالتحقق من التشابه أو الانتحال في الأبحاث والمقالات العلمية والأطروحات الجامعية والكتب والأبحاث باللغة العربية، وتحديد درجة التشابه أو أصالة الأعمال البحثية وحماية ملكيتها الفكرية. تعرف اكثر