Time and cost overruns in Jordanian buliding construction projects

العناوين الأخرى

تجاوز الوقت و التكلفة في المشاريع الإنشائية للأبنية الأردنية

المؤلفون المشاركون

al-Tarawinah, Sultan Abd al-Rahman Dhiyab
al-Tarawinah, Isra Radi
al-Sarayirah, Muhammad

المصدر

Mu'tah Journal for Research and Studies : Natural and Applied Sciences Series

العدد

المجلد 35، العدد 1 (30 يونيو/حزيران 2020)، ص ص. 53-73، 21ص.

الناشر

جامعة مؤتة عمادة البحث العلمي

تاريخ النشر

2020-06-30

دولة النشر

الأردن

عدد الصفحات

21

التخصصات الرئيسية

الهندسة المدنية

الملخص EN

Construction industry supports investment in Jordan, and Arab countries.

Professional practices of construction parties highly affect the performance of construction process.

Time delay and cost overrun are the most important performance measures in construction process.

Current research aims at identifying the main expected factors that affect and cause time delay and cost overrun in building projects in Jordan.

A group of 12 experts from all firms were selected to identify these factors in a questionnaire designed for the purpose of research.

150 copies of the questionnaire were prepared and sent to the personnel in each party (clients, consultants, and contractors) to rank these factors.

Through the analysis, individual rank was calculated for each factor given by each party separately.

A group factor (financial, design, technical, management, external, competency, workmanship, communication, material, site, and regulation) issues were calculated.

A comparative test between means of ranks was conducted among clients, consultants, and contractors to test the significance of difference between means if exists.

Clients agree with contractors that financial and competency issues have a great effect on time delay and cost overrun.

Also, clients agree with consultants that design issues have a great effect on time delay and cost overrun.

In addition, consultants see that workmanship issues have a great effect on time delay and cost overrun also.

Results will be of great help for contract parties and engineers to avoid time delay and/or cost overrun in planning for or administrating projects.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

al-Tarawinah, Sultan Abd al-Rahman Dhiyab& al-Sarayirah, Muhammad& al-Tarawinah, Isra Radi. 2020. Time and cost overruns in Jordanian buliding construction projects. Mu'tah Journal for Research and Studies : Natural and Applied Sciences Series،Vol. 35, no. 1, pp.53-73.
https://search.emarefa.net/detail/BIM-964057

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

al-Tarawinah, Sultan Abd al-Rahman Dhiyab…[et al.]. Time and cost overruns in Jordanian buliding construction projects. Mu'tah Journal for Research and Studies : Natural and Applied Sciences Series Vol. 35, no. 1 (2020), pp.53-73.
https://search.emarefa.net/detail/BIM-964057

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

al-Tarawinah, Sultan Abd al-Rahman Dhiyab& al-Sarayirah, Muhammad& al-Tarawinah, Isra Radi. Time and cost overruns in Jordanian buliding construction projects. Mu'tah Journal for Research and Studies : Natural and Applied Sciences Series. 2020. Vol. 35, no. 1, pp.53-73.
https://search.emarefa.net/detail/BIM-964057

نوع البيانات

مقالات

لغة النص

الإنجليزية

الملاحظات

Includes appendix : p. 69-73

رقم السجل

BIM-964057