Solutions proposed for the navigation problem downstream Zefta barrages

Other Title(s)

حلول مقترحة لمشكلة المالحة خلف قناطر زفتا

Joint Authors

Haykal, Nasr
Fahmi, Wail A.

Source

Journal of Engineering Sciences

Issue

Vol. 48, Issue 6 (30 Nov. 2020), pp.998-1023, 26 p.

Publisher

Assiut University Faculty of Engineering

Publication Date

2020-11-30

Country of Publication

Egypt

No. of Pages

26

Main Subjects

Engineering & Technology Sciences (Multidisciplinary)

Abstract EN

The Nile navigable Damietta branch extends between Cairo and Damietta open seaport on the Mediterranean.

For safe navigation throughout the branch, a 2.30 m minimum flow depth (MFD) is required.

A recovery project to improve the branch navigation was started in 1999 and completed in 2005.

The project was to implement a 40 m wide navigable waterway.

About 6.50 million m3 of bed materials had been removed from bottlenecks at $ 18.20 million cost.

In 2003, the construction of a new lock of 150.0 m length, 17.0 m width and (1.50) m bed level was completed on Zefta Barrages (ZB) east side to meet the navigation requirements.

The barrages are located at Km 119.625 downstream (D/S) El-Roda Gauge in Cairo.

However, the resulting water stage (WS) D/S (ZB) during low discharges was insufficient to provide the MFD.

Field studies were conducted to reveal the reasons.

They found the branch flow carrying capacity had increased due to excessive dredging which caused a decline in WSs D/S (ZB).

Analyzing the hydrologic and topographic conditions, two solution concepts were reached; either to raise the WS by 0.70 m or to lower the bed level of the diversion channel located D/S the new lock by 1.0 m.

Therefore, this study aims to introduce solutions to overcome the problem.

The solutions are to use a D/S rubber weir for raising the WS or construct a new lock within the D/S diversion channel for lowering the bed level or build new barrages with a new lock.

American Psychological Association (APA)

Fahmi, Wail A.& Haykal, Nasr. 2020. Solutions proposed for the navigation problem downstream Zefta barrages. Journal of Engineering Sciences،Vol. 48, no. 6, pp.998-1023.
https://search.emarefa.net/detail/BIM-1000309

Modern Language Association (MLA)

Fahmi, Wail A.& Haykal, Nasr. Solutions proposed for the navigation problem downstream Zefta barrages. Journal of Engineering Sciences Vol. 48, no. 6 (Nov. 2020), pp.998-1023.
https://search.emarefa.net/detail/BIM-1000309

American Medical Association (AMA)

Fahmi, Wail A.& Haykal, Nasr. Solutions proposed for the navigation problem downstream Zefta barrages. Journal of Engineering Sciences. 2020. Vol. 48, no. 6, pp.998-1023.
https://search.emarefa.net/detail/BIM-1000309

Data Type

Journal Articles

Language

English

Notes

-

Record ID

BIM-1000309