Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms
Joint Authors
Jung, Youngsoo
Moon, Byeong-Suk
Kim, Yun-Myung
Kim, Woojoong
Source
Science and Technology of Nuclear Installations
Issue
Vol. 2015, Issue 2015 (31 Dec. 2015), pp.1-13, 13 p.
Publisher
Hindawi Publishing Corporation
Publication Date
2015-03-04
Country of Publication
Egypt
No. of Pages
13
Abstract EN
As the owners expect that the cost and time for nuclear power plant construction would decrease with new entrants into the market, there will be severer competition in the nuclear industry.
In order to achieve performance improvement and to attain competitive advantages under the globalized competition, practitioners and researchers in the nuclear industry have recently exerted efforts to develop an advanced and efficient management methodology for the nuclear mega-projects.
Among several candidates, integrated cost and schedule control system is of great concern because it can effectively manage the three most important project performances including cost, time, and quality.
In this context, the purpose of this paper is to develop a project numbering system (PNS) of integrated cost and schedule control system for nuclear power plant construction.
Distinct attributes of nuclear power plant construction were investigated first in order to identify influencing variables that characterize real-world implementation of advanced cost and schedule controls.
A scenario was then developed and analysed to simulate a case-project.
By using this case-project, proposed management requirements, management methods, measurement techniques, data structure, and data collection methods for integrated cost and schedule PNS were illustrated.
Finally, findings and implications are outlined, and recommendations for further research are presented.
American Psychological Association (APA)
Jung, Youngsoo& Moon, Byeong-Suk& Kim, Yun-Myung& Kim, Woojoong. 2015. Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms. Science and Technology of Nuclear Installations،Vol. 2015, no. 2015, pp.1-13.
https://search.emarefa.net/detail/BIM-1077819
Modern Language Association (MLA)
Jung, Youngsoo…[et al.]. Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms. Science and Technology of Nuclear Installations No. 2015 (2015), pp.1-13.
https://search.emarefa.net/detail/BIM-1077819
American Medical Association (AMA)
Jung, Youngsoo& Moon, Byeong-Suk& Kim, Yun-Myung& Kim, Woojoong. Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms. Science and Technology of Nuclear Installations. 2015. Vol. 2015, no. 2015, pp.1-13.
https://search.emarefa.net/detail/BIM-1077819
Data Type
Journal Articles
Language
English
Notes
Includes bibliographical references
Record ID
BIM-1077819