A new heuristic for scheduling optimization of non-repetitive construction projects under constrained resources

Time cited in Arcif : 
1

Joint Authors

Harun, Ahmad al-Amin
Mahmud, Salma Y. M.
Luqman, Adil Hasan A.

Source

Journal of Science and Technology : in Engineering and Computer Sciences

Issue

Vol. 16, Issue 1 (30 Jun. 2015), pp.14-28, 15 p.

Publisher

Sudan University of Science and Technology Deanship of Scientific Research

Publication Date

2015-06-30

Country of Publication

Sudan

No. of Pages

15

Main Subjects

Business Administration
Civil Engineering

Topics

Abstract AR

ظلت أطراف مثلث التشييد (المارك و المقاول و الاستشاري) في السودان يعانون و باستمرار من مشكلة الإطالة في زمن إكمال المشروع و بصورة خاصة في حالة الموارد المحدودة أو المقيدة مما ينتج عنه اختلاف بين الأطراف الثلاثة و من ثم يقود هذا إلى التأخير في زمن إكمال المشروع مما يؤدي بالضرورة إلى ارتفاع تكلفته الكلية في نهاية الأمر.

لحل هذه المشكلة فإنه تم جمع و محاكاة و تحليل معلومات من عشرة مشاريع إنشائية نفذت في ولاية الخرطوم و بعض المدن الأخرى.

تم استخدام برنامج البرايمافيرا (Primavera) كأداة للمحاكاة ثم طبقت ستة عشرة فرضية (Heuristic) تم اختيارها على المشاريع العشرة.

تم استخدام وسائل إحصائية و وسائل بحوث العمليات مع الفرضيات (Heuristic) مع الوضع في الاعتبار أن أفضل التطبيقات السائدة في صناعة التشييد قد تم استخدامها.

من ثم تم استخدام برنامج الكمبيوتر(Lindo كأداة لصنع القرار) للوصول للحل الأمثل المطلوب و هو الحصول على أقل زمن ممكن لإكمال المشروع في حالة الموارد المقيدة.

تم تحليل النتائج و التي خلصت إلى أن الحل الأمثل للزمن الإضافي المطلوب في معدله الأدنى لإكمال المشروع (في حالة الموارد المقيدة) قد تم تحقيقه كنتيجة لتطبيق فرضية (Heuristic) أقل زمن بدء متأخر (Minimum late start time).

إن هذه الفرضية الجديدة المختارة تمثل جدولة زمنية مثلي لمشاريع غير متكررة باعتبار حالة الموارد المقيدة.

Abstract EN

In Sudan, the clients, contractors and consultants (stakeholders) suffer from the elongation of project completion time, especially in the case of limited resources.

This problem results in the conflict among them, and hence leads to project delay that consequently influences the overall project cost.

To solve this problem, data from ten construction projects executed in Khartoum state and other towns was collected, simulated and analyzed.

Primavera software program was used as a simulator tool and sixteen selected heuristics were applied to the ten projects.

Statistical and operational research tools combined with the existing heuristics, while considering best common practices in construction industry, were used.

Lindo software, as a decision making tool, is then used to find the optimum solution, i.e., finding the minimum time to complete the project under limited resources.

The results were then evaluated and, hence, concluded that the optimum solution of the extra needed time at its minimum possible rate (to complete the project under limited resources) was achieved as a result of implementing the heuristic of “minimum late start time”.

This new “selected” heuristic optimizes the scheduling time of non-repetitive projects while considering the availability of limited resources.

American Psychological Association (APA)

Luqman, Adil Hasan A.& Harun, Ahmad al-Amin& Mahmud, Salma Y. M.. 2015. A new heuristic for scheduling optimization of non-repetitive construction projects under constrained resources. Journal of Science and Technology : in Engineering and Computer Sciences،Vol. 16, no. 1, pp.14-28.
https://search.emarefa.net/detail/BIM-439818

Modern Language Association (MLA)

Luqman, Adil Hasan A.…[et al.]. A new heuristic for scheduling optimization of non-repetitive construction projects under constrained resources. Journal of Science and Technology : in Engineering and Computer Sciences Vol. 16, no. 1 (2015), pp.14-28.
https://search.emarefa.net/detail/BIM-439818

American Medical Association (AMA)

Luqman, Adil Hasan A.& Harun, Ahmad al-Amin& Mahmud, Salma Y. M.. A new heuristic for scheduling optimization of non-repetitive construction projects under constrained resources. Journal of Science and Technology : in Engineering and Computer Sciences. 2015. Vol. 16, no. 1, pp.14-28.
https://search.emarefa.net/detail/BIM-439818

Data Type

Journal Articles

Language

English

Notes

Includes appendix : p. 24-28

Record ID

BIM-439818