Branch and Bound Algorithms for Resource Constrained Project Scheduling Problem Subject to Nonrenewable Resources with Prescheduled Procurement

Joint Authors

Shadrokh, S.
Fathi, Y.
Shirzadeh Chaleshtarti, A.

Source

Mathematical Problems in Engineering

Issue

Vol. 2014, Issue 2014 (31 Dec. 2014), pp.1-15, 15 p.

Publisher

Hindawi Publishing Corporation

Publication Date

2014-02-27

Country of Publication

Egypt

No. of Pages

15

Main Subjects

Civil Engineering

Abstract EN

A lot of projects in real life are subject to some kinds of nonrenewable resources that are not exactly similar to the type defined in the project scheduling literature.

The difference stems from the fact that, in those projects, contrary to the common assumption in the project scheduling literature, nonrenewable resources are not available in full amount at the beginning of the project, but they are procured along the project horizon.

In this paper, we study this different type of nonrenewable resources.

To that end, we extend the resource constrained project scheduling problem (RCPSP) by this resource type (RCPSP-NR) and customize four basic branch and bound algorithms of RCPSP for it, including precedence tree, extension alternatives, minimal delaying alternatives, and minimal forbidden sets.

Several bounding and fathoming rules are introduced to the algorithms to shorten the enumeration process.

We perform comprehensive experimental analysis using the four customized algorithms and also CPLEX solver.

American Psychological Association (APA)

Shirzadeh Chaleshtarti, A.& Shadrokh, S.& Fathi, Y.. 2014. Branch and Bound Algorithms for Resource Constrained Project Scheduling Problem Subject to Nonrenewable Resources with Prescheduled Procurement. Mathematical Problems in Engineering،Vol. 2014, no. 2014, pp.1-15.
https://search.emarefa.net/detail/BIM-486873

Modern Language Association (MLA)

Shirzadeh Chaleshtarti, A.…[et al.]. Branch and Bound Algorithms for Resource Constrained Project Scheduling Problem Subject to Nonrenewable Resources with Prescheduled Procurement. Mathematical Problems in Engineering No. 2014 (2014), pp.1-15.
https://search.emarefa.net/detail/BIM-486873

American Medical Association (AMA)

Shirzadeh Chaleshtarti, A.& Shadrokh, S.& Fathi, Y.. Branch and Bound Algorithms for Resource Constrained Project Scheduling Problem Subject to Nonrenewable Resources with Prescheduled Procurement. Mathematical Problems in Engineering. 2014. Vol. 2014, no. 2014, pp.1-15.
https://search.emarefa.net/detail/BIM-486873

Data Type

Journal Articles

Language

English

Notes

Includes bibliographical references

Record ID

BIM-486873