Multimode Preemptive Resource Investment Problem Subject to Due Dates for Activities: Formulation and Solution Procedure
المؤلفون المشاركون
Arani, Mohammad
Afshar-Nadjafi, Behrouz
المصدر
Advances in Operations Research
العدد
المجلد 2014، العدد 2014 (31 ديسمبر/كانون الأول 2014)، ص ص. 1-10، 10ص.
الناشر
Hindawi Publishing Corporation
تاريخ النشر
2014-09-29
دولة النشر
مصر
عدد الصفحات
10
التخصصات الرئيسية
تكنولوجيا المعلومات وعلم الحاسوب
الملخص EN
The preemptive Multimode resource investment problem is investigated.
The Objective is to minimize the total renewable/nonrenewable resource costs and earliness-tardiness costs by a given project deadline and due dates for activities.
In this problem setting preemption is allowed with no setup cost or time.
The project contains activities interrelated by finish-start type precedence relations with a time lag of zero, which require a set of renewable and nonrenewable resources.
The problem formed in this way is an NP-hard.
A mixed integer programming formulation is proposed for the problem and parameters tuned genetic algorithm (GA) is proposed to solve it.
To evaluate the performance of the proposed algorithm, 120 test problems are used.
Comparative statistical results reveal that the proposed GA is efficient and effective in terms of the objective function and computational times.
نمط استشهاد جمعية علماء النفس الأمريكية (APA)
Afshar-Nadjafi, Behrouz& Arani, Mohammad. 2014. Multimode Preemptive Resource Investment Problem Subject to Due Dates for Activities: Formulation and Solution Procedure. Advances in Operations Research،Vol. 2014, no. 2014, pp.1-10.
https://search.emarefa.net/detail/BIM-1034340
نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)
Afshar-Nadjafi, Behrouz& Arani, Mohammad. Multimode Preemptive Resource Investment Problem Subject to Due Dates for Activities: Formulation and Solution Procedure. Advances in Operations Research No. 2014 (2014), pp.1-10.
https://search.emarefa.net/detail/BIM-1034340
نمط استشهاد الجمعية الطبية الأمريكية (AMA)
Afshar-Nadjafi, Behrouz& Arani, Mohammad. Multimode Preemptive Resource Investment Problem Subject to Due Dates for Activities: Formulation and Solution Procedure. Advances in Operations Research. 2014. Vol. 2014, no. 2014, pp.1-10.
https://search.emarefa.net/detail/BIM-1034340
نوع البيانات
مقالات
لغة النص
الإنجليزية
الملاحظات
Includes bibliographical references
رقم السجل
BIM-1034340
قاعدة معامل التأثير والاستشهادات المرجعية العربي "ارسيف Arcif"
أضخم قاعدة بيانات عربية للاستشهادات المرجعية للمجلات العلمية المحكمة الصادرة في العالم العربي
![](/images/ebook-kashef.png)
تقوم هذه الخدمة بالتحقق من التشابه أو الانتحال في الأبحاث والمقالات العلمية والأطروحات الجامعية والكتب والأبحاث باللغة العربية، وتحديد درجة التشابه أو أصالة الأعمال البحثية وحماية ملكيتها الفكرية. تعرف اكثر
![](/images/kashef-image.png)