Resource Tardiness Weighted Cost Minimization in Project Scheduling

المؤلف

Shirzadeh Chaleshtarti, A.

المصدر

Advances in Operations Research

العدد

المجلد 2017، العدد 2017 (31 ديسمبر/كانون الأول 2017)، ص ص. 1-11، 11ص.

الناشر

Hindawi Publishing Corporation

تاريخ النشر

2017-01-10

دولة النشر

مصر

عدد الصفحات

11

التخصصات الرئيسية

تكنولوجيا المعلومات وعلم الحاسوب

الملخص EN

In this paper, we study a project scheduling problem that is called resource constrained project scheduling problem under minimization of total weighted resource tardiness penalty cost (RCPSP-TWRTPC).

In this problem, the project is subject to renewable resources, each renewable resource is available for limited time periods during the project life cycle, and keeping the resource for each extra period results in some tardiness penalty cost.

We introduce a branch and bound algorithm to solve the problem exactly and use several bounding, fathoming, and dominance rules in our algorithm to shorten the enumeration process.

We point out parameters affecting the RCPSP-TWRTPC degree of difficulty, generate extensive sets of sample instances for the problem, and perform comprehensive experimental analysis using the customized algorithm and also CPLEX solver.

We analyze the algorithm behavior with respect to the changes in instances degree of difficulty and compare its performance for different cases with the CPLEX solver.

The results reveal algorithm efficiency.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

Shirzadeh Chaleshtarti, A.. 2017. Resource Tardiness Weighted Cost Minimization in Project Scheduling. Advances in Operations Research،Vol. 2017, no. 2017, pp.1-11.
https://search.emarefa.net/detail/BIM-1125212

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

Shirzadeh Chaleshtarti, A.. Resource Tardiness Weighted Cost Minimization in Project Scheduling. Advances in Operations Research No. 2017 (2017), pp.1-11.
https://search.emarefa.net/detail/BIM-1125212

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

Shirzadeh Chaleshtarti, A.. Resource Tardiness Weighted Cost Minimization in Project Scheduling. Advances in Operations Research. 2017. Vol. 2017, no. 2017, pp.1-11.
https://search.emarefa.net/detail/BIM-1125212

نوع البيانات

مقالات

لغة النص

الإنجليزية

الملاحظات

Includes bibliographical references

رقم السجل

BIM-1125212