Causes of Delay in the Construction Projects of Subway Tunnel

المؤلفون المشاركون

Cheng, Tao
Zhang, Hang
Zhang, Dingbang

المصدر

Advances in Civil Engineering

العدد

المجلد 2020، العدد 2020 (31 ديسمبر/كانون الأول 2020)، ص ص. 1-14، 14ص.

الناشر

Hindawi Publishing Corporation

تاريخ النشر

2020-11-20

دولة النشر

مصر

عدد الصفحات

14

التخصصات الرئيسية

هندسة مدنية

الملخص EN

The constructions of urban infrastructure are an important sector that provides remarkable ingredients for the economic development of modern cities.

However, a large number of transportation infrastructure construction projects are delayed; therefore, those projects always exceed their original time and cost estimates.

So construction delay has been considered as a recurring problem in the construction projects of urban infrastructure, and it adversely affects the time, cost, safety, and quality of construction.

This paper is committed to investigating the time performance of subway tunnel constructions in China to identify the causes of delay based on the questionnaire surveys of 87 tunnel consultants and 91 contractors, and a total of 49 delay causes of tunnel construction are identified one by one in this study.

It can be concluded from this study that the six most severe delay causes are national policy for subway tunnel construction, complicated geological conditions, payment delays by owners, award projects to the lowest bid price, shortage of advanced large equipment, and low productivity of laborers.

There is a relatively reliable agreement between the tunnel consultants and contractors of 76.3% on the ranking of different delay causes.

نمط استشهاد جمعية علماء النفس الأمريكية (APA)

Zhang, Dingbang& Zhang, Hang& Cheng, Tao. 2020. Causes of Delay in the Construction Projects of Subway Tunnel. Advances in Civil Engineering،Vol. 2020, no. 2020, pp.1-14.
https://search.emarefa.net/detail/BIM-1125214

نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)

Zhang, Dingbang…[et al.]. Causes of Delay in the Construction Projects of Subway Tunnel. Advances in Civil Engineering No. 2020 (2020), pp.1-14.
https://search.emarefa.net/detail/BIM-1125214

نمط استشهاد الجمعية الطبية الأمريكية (AMA)

Zhang, Dingbang& Zhang, Hang& Cheng, Tao. Causes of Delay in the Construction Projects of Subway Tunnel. Advances in Civil Engineering. 2020. Vol. 2020, no. 2020, pp.1-14.
https://search.emarefa.net/detail/BIM-1125214

نوع البيانات

مقالات

لغة النص

الإنجليزية

الملاحظات

Includes bibliographical references

رقم السجل

BIM-1125214