Causes of Delay in the Construction Projects of Subway Tunnel

Joint Authors

Cheng, Tao
Zhang, Hang
Zhang, Dingbang

Source

Advances in Civil Engineering

Issue

Vol. 2020, Issue 2020 (31 Dec. 2020), pp.1-14, 14 p.

Publisher

Hindawi Publishing Corporation

Publication Date

2020-11-20

Country of Publication

Egypt

No. of Pages

14

Main Subjects

Civil Engineering

Abstract EN

The constructions of urban infrastructure are an important sector that provides remarkable ingredients for the economic development of modern cities.

However, a large number of transportation infrastructure construction projects are delayed; therefore, those projects always exceed their original time and cost estimates.

So construction delay has been considered as a recurring problem in the construction projects of urban infrastructure, and it adversely affects the time, cost, safety, and quality of construction.

This paper is committed to investigating the time performance of subway tunnel constructions in China to identify the causes of delay based on the questionnaire surveys of 87 tunnel consultants and 91 contractors, and a total of 49 delay causes of tunnel construction are identified one by one in this study.

It can be concluded from this study that the six most severe delay causes are national policy for subway tunnel construction, complicated geological conditions, payment delays by owners, award projects to the lowest bid price, shortage of advanced large equipment, and low productivity of laborers.

There is a relatively reliable agreement between the tunnel consultants and contractors of 76.3% on the ranking of different delay causes.

American Psychological Association (APA)

Zhang, Dingbang& Zhang, Hang& Cheng, Tao. 2020. Causes of Delay in the Construction Projects of Subway Tunnel. Advances in Civil Engineering،Vol. 2020, no. 2020, pp.1-14.
https://search.emarefa.net/detail/BIM-1125214

Modern Language Association (MLA)

Zhang, Dingbang…[et al.]. Causes of Delay in the Construction Projects of Subway Tunnel. Advances in Civil Engineering No. 2020 (2020), pp.1-14.
https://search.emarefa.net/detail/BIM-1125214

American Medical Association (AMA)

Zhang, Dingbang& Zhang, Hang& Cheng, Tao. Causes of Delay in the Construction Projects of Subway Tunnel. Advances in Civil Engineering. 2020. Vol. 2020, no. 2020, pp.1-14.
https://search.emarefa.net/detail/BIM-1125214

Data Type

Journal Articles

Language

English

Notes

Includes bibliographical references

Record ID

BIM-1125214