Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast
المؤلفون المشاركون
Sebastian, Miguel A.
Urgilés, P.
Claver, J.
المصدر
العدد
المجلد 2019، العدد 2019 (31 ديسمبر/كانون الأول 2019)، ص ص. 1-11، 11ص.
الناشر
Hindawi Publishing Corporation
تاريخ النشر
2019-04-01
دولة النشر
مصر
عدد الصفحات
11
التخصصات الرئيسية
الملخص EN
All projects take place within a context of uncertainty.
That is especially noticeable in complex hydroelectric power generation projects, which are affected by factors such as the large number of multidisciplinary tasks to be performed in parallel, long execution times, or the risks inherent in various fields like geology, hydrology, and structural, electrical, and mechanical engineering, among others.
Such factors often lead to cost overruns and delays in projects of this type.
This paper analyzes the efficiency of the Earned Value Management technique and its Earned Schedule extension, as means of forecasting costs and deadlines when applied to complex hydroelectric power production projects.
It is worth noting that this analysis was based on simulation models applied to real-life projects.
The results showed that cost forecasting becomes very accurate over time, whereas duration forecasting is not reliably accurate.
نمط استشهاد جمعية علماء النفس الأمريكية (APA)
Urgilés, P.& Claver, J.& Sebastian, Miguel A.. 2019. Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast. Complexity،Vol. 2019, no. 2019, pp.1-11.
https://search.emarefa.net/detail/BIM-1131351
نمط استشهاد الجمعية الأمريكية للغات الحديثة (MLA)
Urgilés, P.…[et al.]. Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast. Complexity No. 2019 (2019), pp.1-11.
https://search.emarefa.net/detail/BIM-1131351
نمط استشهاد الجمعية الطبية الأمريكية (AMA)
Urgilés, P.& Claver, J.& Sebastian, Miguel A.. Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast. Complexity. 2019. Vol. 2019, no. 2019, pp.1-11.
https://search.emarefa.net/detail/BIM-1131351
نوع البيانات
مقالات
لغة النص
الإنجليزية
الملاحظات
Includes bibliographical references
رقم السجل
BIM-1131351
قاعدة معامل التأثير والاستشهادات المرجعية العربي "ارسيف Arcif"
أضخم قاعدة بيانات عربية للاستشهادات المرجعية للمجلات العلمية المحكمة الصادرة في العالم العربي
تقوم هذه الخدمة بالتحقق من التشابه أو الانتحال في الأبحاث والمقالات العلمية والأطروحات الجامعية والكتب والأبحاث باللغة العربية، وتحديد درجة التشابه أو أصالة الأعمال البحثية وحماية ملكيتها الفكرية. تعرف اكثر